Title: Adopt a resolution authorizing: A) Job Order Contract Agreements with Devaney Engineering, Inc., Agbayani Construction Corporation, and Yerba Buena Engineering & Construction, Inc., for Engineering, Construction, Roads, and Utilities for Capital Projects, for the term of March 23, 2021 through March 22, 2022, each in an amount not to exceed $3,000,000; and B) The Construction Task Catalogs, specifications, and conformance with prevailing wage scale requirements for Engineering, Construction, Roads, and Utilities for Capital Projects Job Order Contracts; and C) The Director of Public Works, or designee, to issue Work/Job Orders, execute Change/Revision Orders, and make financial and administrative changes to executed Job Order Contract agreements.
Attachments: 1. 20210323_r_JOCs 2120-2122_final, 2. 20210323_att_JOCs 2120-2122
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: James C. Porter, Director of Public Works
Subject: On-Call Job Order Contract Agreements and Adoption of the Job Order Contracts Task Catalog


RECOMMENDATION:
title
Adopt a resolution authorizing:

A) Job Order Contract Agreements with Devaney Engineering, Inc., Agbayani Construction Corporation, and Yerba Buena Engineering & Construction, Inc., for Engineering, Construction, Roads, and Utilities for Capital Projects, for the term of March 23, 2021 through March 22, 2022, each in an amount not to exceed $3,000,000; and

B) The Construction Task Catalogs, specifications, and conformance with prevailing wage scale requirements for Engineering, Construction, Roads, and Utilities for Capital Projects Job Order Contracts; and

C) The Director of Public Works, or designee, to issue Work/Job Orders, execute Change/Revision Orders, and make financial and administrative changes to executed Job Order Contract agreements.

body
BACKGROUND:
On November 19, 2013, this Board adopted Resolution No. 072896, which authorized a streamlined process for Job Order Contracts (JOCs), which allows for the preparation of task catalogs, specifications, and bid documents in conformance with prevailing wage scale requirements for JOCs, which may be adopted by this Board at the time the resulting contract is considered for award.

Public Contract Code Section 20128.5 authorizes the Board of Supervisors to award individual annual JOCs for repair, remodeling, or other repetitive work to be done according to unit prices, in an amount not to exceed $3,000,000 (adjusted annually based on changes in the California Consumer Price Index). Since the statute was enacted in 1997, the application of the CPI has resulted in a current maximum amount of $5,000,000 for annual JOCs. Contractors bid adjustment factors are to be applied to the Unit Prices for specific items of work. The c...