Special Notice / Hearing: None__
Vote Required: Majority
To: Honorable Board of Supervisors
From: Michael Callagy, County Manager
Adam Ely, Project Development Unit Director
Subject: Amendment to Truebeck Construction, Inc. Contract for Lathrop House Relocation; Ratification of Amendments
RECOMMENDATION:
title
Adopt a resolution authorizing the:
A) President of the Board of Supervisors to amend the agreement with Truebeck Construction, Inc., increasing the agreement by an amount not-to-exceed $240,420, for final costs associated with the Lathrop House Relocation Project establishing a Guaranteed Maximum Price of $1,512,092; and
B) Ratification of Amendment 2 to the Agreement with Truebeck Construction, Inc.
body
BACKGROUND:
In 2017, this Board held a study session to consider capital projects recommended in feasibility and master plan studies to address: (1) aging and deteriorating facilities (2) overuse of lease space; (3) seismic compliance; (4) public accessibility and navigation; (5) rising environmental standards; (6) projected staff growth; and (7) a need to modernize public and employee spaces. This Board directed staff to pursue projects, including County Office Building 3 (COB3), Parking Structure 2 (PS2) and Lathrop House Relocation project.
In June 2018, this Board approved Resolution 075918 authorizing an agreement with Truebeck Construction, Inc. (Truebeck) for construction management of COB3 and PS2 for a total amount of $19,349,663, with change order authority not exceed an additional $1,934,966.
In June 2018, the County received and rejected overbudget bids for a stand-alone Lathrop House Relocation project. To promote construction, management, and schedule efficiencies, the County solicited a bid from Truebeck to incorporate the Lathrop House Relocation project into the COB3 and PS2 Projects. Following competitive and public subcontractor bidding, the Lathrop House Relocation project scope was incorpora...
Click here for full text