San Mateo County Logo
File #: 20-380    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/5/2020 Departments: PUBLIC WORKS
On agenda: 6/2/2020 Final action: 6/2/2020
Title: Adopt a resolution: A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the 2020 Countywide Cape Seal and Microsurfacing Project; and B) Authorizing the President of the Board to execute an agreement with Pavement Coatings Co., in the amount of $1,359,072 for the 2020 Countywide Cape Seal and Microsurfacing Project; and C) Authorizing the Director of Public Works to: 1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $135,908, or approximately 10 percent of the agreement amount; and 2. File a Notice of Exemption for a California Environmental Quality Act Categorical Exemption.
Attachments: 1. 20200602_r_2020 Countywide Cape Seal and Microsurfacing Project_5-22-20, 2. 20200602_att_2020 Countywide Cape Seal and Microsurfacing Project_Exhibit A, 3. 20200602_att_2020 Countywide Cape Seal and Microsurfacing Project_Exhibit B
Special Notice / Hearing: None
Vote Required: Majority

To: Honorable Board of Supervisors
From: James C. Porter, Director of Public Works
Subject: 2020 Countywide Cape Seal and Microsurfacing Project
[County Project No. RW923; Project File No. E5020]


RECOMMENDATION:
title
Adopt a resolution:

A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the 2020 Countywide Cape Seal and Microsurfacing Project; and

B) Authorizing the President of the Board to execute an agreement with Pavement Coatings Co., in the amount of $1,359,072 for the 2020 Countywide Cape Seal and Microsurfacing Project; and

C) Authorizing the Director of Public Works to:

1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $135,908, or approximately 10 percent of the agreement amount; and

2. File a Notice of Exemption for a California Environmental Quality Act Categorical Exemption.

body
BACKGROUND:
On March 10, 2020, your Board adopted Resolution No. 077292, which "streamlined" the bid process for projects to be constructed during the 2020 construction season. The projects are maintenance type projects that do not have long lead times for design, are not considered controversial requiring specific property owner input, and that do not require state or federal grant approvals, which have not previously been approved by your Board, or require extensive permit approvals from regulatory agencies. Authorizing the Director of Public Works to develop plans and specifications and to call for bids for these types of projects at one time reduces overall project delivery schedules and administrative staff time for these types of projects.


DISCUSSION:
This Project involves repairing specific road areas or potholes, constructing or reconstructing sidewalk access ramps where necessary, and applying a Cape Seal or Microsurfacing ...

Click here for full text