File #: 19-710    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/13/2019 Departments: PUBLIC WORKS
On agenda: 7/9/2019 Final action: 7/9/2019
Title: Adopt a resolution: A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the Reconstruction and Cape Seal of Madrid Avenue, Sevilla Avenue, and Sonora Avenue Project in the El Granada Area; and B) Authorizing the President of the Board to execute an agreement with Granite Rock Company, in the amount of $685,186 for the Reconstruction and Cape Seal of Madrid Avenue, Sevilla Avenue, and Sonora Avenue Project in the El Granada Area; and C) Authorizing the Director of Public Works to: 1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $68,519.00, or approximately 10 percent of the agreement amount; and 2. File a Notice of Exemption for a California Environmental Quality Act Categorical Exemption.
Attachments: 1. 20190709_r_Recon Madrid Sevilla Sonora_Award, 2. 20190709_att_Recon Madrid Sevilla Sonora_Award_Exhibit A
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: James C. Porter, Director of Public Works
Subject: Agreement with Granite Rock Company for the Reconstruction and Cape Seal of Madrid Avenue, Sevilla Avenue, and Sonora Avenue Project in the El Granada Area, [County Project No. RW803, Project File No. E4987000]

RECOMMENDATION:
title
Adopt a resolution:

A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the Reconstruction and Cape Seal of Madrid Avenue, Sevilla Avenue, and Sonora Avenue Project in the El Granada Area; and

B) Authorizing the President of the Board to execute an agreement with Granite Rock Company, in the amount of $685,186 for the Reconstruction and Cape Seal of Madrid Avenue, Sevilla Avenue, and Sonora Avenue Project in the El Granada Area; and

C) Authorizing the Director of Public Works to:

1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $68,519.00, or approximately 10 percent of the agreement amount; and

2. File a Notice of Exemption for a California Environmental Quality Act Categorical Exemption.

body
BACKGROUND:
On January 23, 2018 and March 26, 2019, your Board adopted Resolution Nos. 075689 and 076510, which "streamlined" the bid process for projects to be constructed during the 2018 and 2019 construction seasons, respectively.

The projects are maintenance-type projects that do not have long lead times for design, are not considered controversial requiring specific property owner input, and that do not require state or federal grant approvals, which have not previously been approved by your Board, or require extensive permit approvals from regulatory agencies. Authorizing the Director of Public Works to develop plans and specifications and to call for bids for these types of projects at one time, reduces overall project ...