San Mateo County Logo
File #: 19-528    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/29/2019 Departments: PUBLIC WORKS
On agenda: 6/4/2019 Final action: 6/4/2019
Title: Adopt a resolution: A) Adopting the plans and specifications, including conformance with prevailing wage scale requirements, for the Memorial Park Wastewater Treatment Facilities Improvement Project (WWTP Project); and B) Authorizing the President of the Board to execute an agreement with Anderson Pacific Engineering Construction, Inc., in the amount of $2,824,780 for the Memorial Park Wastewater Treatment Facilities Improvement Project (WWTP Project); and C) Authorizing the Director of Public Works to execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $282,478, or approximately 10 percent of the agreement amount.
Attachments: 1. 20190604_r_Memorial Award, 2. 20190604_att_Exhibit A
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: James C. Porter, Director of Public Works
Subject: Agreement with Anderson Pacific Engineering Construction, Inc. for the Memorial Park Wastewater Treatment Facilities Improvement Project [County Project No. P23P4, Project File No. E4955]

RECOMMENDATION:
title
Adopt a resolution:

A) Adopting the plans and specifications, including conformance with prevailing wage scale requirements, for the Memorial Park Wastewater Treatment Facilities Improvement Project (WWTP Project); and

B) Authorizing the President of the Board to execute an agreement with Anderson Pacific Engineering Construction, Inc., in the amount of $2,824,780 for the Memorial Park Wastewater Treatment Facilities Improvement Project (WWTP Project); and

C) Authorizing the Director of Public Works to execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $282,478, or approximately 10 percent of the agreement amount.

body
BACKGROUND:
On January 10, 2017, your Board adopted Resolution No. 074982, which authorized an agreement with Hydroscience Engineers, Inc. to provide services that included: condition assessment of existing wastewater infrastructure, field surveys, geotechnical investigation, environmental analysis and permitting (California Environmental Quality Act compliance), feasibility study, conceptual design, preparation of construction plans, specifications and cost estimates for bidding purposes and construction management and support for the Memorial Park Wastewater Treatment Facilities Improvement Project (Project).

On April 23, 2019, your Board adopted Resolution No. 076548, which certified the Initial Study/Mitigated Negative Declaration for the Memorial Park Wastewater Treatment Facilities Improvement Project and authorized the Director of Public Works to prepare the plans and specifica...