San Mateo County Logo
File #: 19-432    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/11/2019 Departments: PUBLIC WORKS
On agenda: 5/14/2019 Final action:
Title: Adopt a resolution: A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the 2019 Bayside Cape and Slurry Seal Project; and B) Authorizing the President of the Board to execute an agreement with Pavement Coatings Co., in the amount of $1,661,025.00 for the 2019 Bayside Cape and Slurry Seal Project; and C) Authorizing the Director of Public Works to: 1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $166,103.00, or approximately 10% of the agreement amount; and 2. File a Notice of Exemption for a California Environmental Quality Act Categorical Exemption.
Attachments: 1. 20190514_att_Plans and Specs Award 2019 Bayside Cape and Slurry Seal - EXHIBIT A, 2. 20190514_att_Plans and Specs Award 2019 Bayside Cape and Slurry Seal - EXHIBIT B, 3. 20190514_r_2019 Countywide Cape Slurry Seal
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Special Notice / Hearing: None
Vote Required: Majority

To: Honorable Board of Supervisors
From: James C. Porter, Director of Public Works
Subject: 2019 Bayside Cape and Slurry Seal Project
[County Project No. RW906; Project File No. E4999]


RECOMMENDATION:
title
Adopt a resolution:

A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the 2019 Bayside Cape and Slurry Seal Project; and

B) Authorizing the President of the Board to execute an agreement with Pavement Coatings Co., in the amount of $1,661,025.00 for the 2019 Bayside Cape and Slurry Seal Project; and

C) Authorizing the Director of Public Works to:

1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $166,103.00, or approximately 10% of the agreement amount; and

2. File a Notice of Exemption for a California Environmental Quality Act Categorical Exemption.

body
BACKGROUND:
On March 26, 2019, your Board adopted Resolution No. 076510, which "streamlined" the bid process for projects to be constructed during the 2019 construction season.

The projects are maintenance-type projects that do not have long lead times for design, are not considered controversial requiring specific property owner input, and that do not require State or federal grant approvals, which have not previously been approved by your Board, or require extensive permit approvals from regulatory agencies. Authorizing the Director of Public Works to develop plans and specifications and to call for bids for these types of projects at one time, reduces overall project delivery schedules and reduces administrative staff time for these types of projects.

DISCUSSION:
On Wednesday May 1, 2019, bids were accepted for this project and subsequently referred to the Department of Public Works (Department) for checking and recommendation. The bid of:

Pavement Coatings Co.
...

Click here for full text