File #: 19-192    Version: 1 Name:
Type: Resolution Status: Passed
File created: 2/6/2019 Departments: PUBLIC WORKS
On agenda: 3/12/2019 Final action: 3/12/2019
Title: Adopt a resolution: A) Adopting the construction task catalog, specifications, and conformance with prevailing wage scale requirements for the 2019 Job Order Contracts for Engineering, Construction, Roads, and Utilities; and B) Authorizing agreements with Granite Rock Company, Andreini Brothers, and Staples Construction for Engineering, Construction, Roads and Utilities, for the term of March 12, 2019 through March 11, 2020, each in an amount not-to-exceed $5,000,000. body
Attachments: 1. 20190312_r_JOCs 1924-1926, 2. 20190312_att_JOCs 1924-1926_Exhibit A

Special Notice / Hearing:    None__

Vote Required:    Majority

 

To:                      Honorable Board of Supervisors

From:                      James C. Porter, Director of Public Works

Subject:                      2019 Job Order Contracts for Engineering, Construction, Roads and Utilities [Job Order Contract Nos. JOC-1924, JOC-1925 and JOC-1926]

 

RECOMMENDATION:

title

Adopt a resolution:

 

A)                     Adopting the construction task catalog, specifications, and conformance with prevailing wage scale requirements for the 2019 Job Order Contracts for Engineering, Construction, Roads, and Utilities; and

 

B)                     Authorizing agreements with Granite Rock Company, Andreini Brothers, and Staples Construction for Engineering, Construction, Roads and Utilities, for the term of March 12, 2019 through March 11, 2020, each in an amount not-to-exceed $5,000,000.

body

body

BACKGROUND:

On November 19, 2013, your Board adopted Resolution No. 072896, which authorized the Director of Public Works to proceed with preparing plans and specifications, conform with prevailing wage scale requirements for Job Order Contracts (JOC), and advertising for bids (streamlined process).

 

Public Contract Code Section 20128.5 authorizes a Board of Supervisors to award individual annual JOCs for repair, remodeling, or other repetitive work to be done according to unit prices, in an amount not to exceed $5,000,000 (adjusted annually based on changes in the California Consumer Price Index). Contractors bid Adjustment Factors to be applied to the Unit Prices for specific items of work. The price of an individual project is determined by multiplying the preset Unit Prices by the appropriate quantities of work and Adjustment Factors.

 

On Thursday, February 21, 2019 at 2:30 p.m., sealed bids were received, accepted and subsequently referred to Public Works for checking and recommendation for JOC-1924, JOC-1925 and JOC-1926 for Engineering, Construction, Roads and Utilities.  The bid documents call for up to three separate JOCs to the three lowest responsible bidders, and each responsible bidder awarded a contract will be declared ineligible for the other contracts.

 

DISCUSSION:

The Department has examined the bids received for the subject JOCs, and determined the lowest responsible bidders for each JOC.

 

The Department will issue individual Job Orders, including a scope of work and a not-to-exceed amount, to the JOC contractors. The not-to-exceed amount for each individual Job Order will vary; however, their cumulative sum will not exceed the maximum amount of the agreement. Any increase above the amount or term of the agreements would be submitted to your Board for consideration.

 

County Counsel has reviewed and approved the resolution and agreements as to form.

 

Approval of this action contributes to the Shared Vision 2025 outcome of Collaborative

Community by reducing the cost and time required to execute major maintenance, repair, and rehabilitation projects on County infrastructure.

 

FISCAL IMPACT:

The terms of these agreements are from March 12, 2019 through March 11, 2020. There is no minimum fiscal obligation for each agreement and the maximum fiscal obligation for each agreement is $5,000,000. The total maximum fiscal obligation for all agreements combined is $15,000,000. The JOC is a requirements agreement. The various individual job orders will be funded through previously approved and appropriated projects.

 

Attachment: Exhibit A - Bid Results