Title: Adopt a resolution authorizing: A) Job Order Contract Agreements with Olympos Painting, Inc., SBAY Construction, Inc., Mark Scott Construction, Inc., and Rodan Builders, Inc. for General Construction; Kinetics Mechanical Service, Inc. and ACCO Engineered Systems for Mechanical Works (HVAC); Platinum Roofing, Inc. and Best Contracting Services, Inc. for Roofing Contracting Services; Century Carpet, Inc. for Flooring Contracting Services; and Kinetics Mechanical Service, Inc. and ACCO Engineered Systems for Plumbing Contracting Services for the term of January 29, 2019 through January 28, 2020, each in an amount not to exceed $5,000,000 for General Construction and Mechanical Works (HVAC), and not to exceed $1,000,000 for Roofing Contracting Services, Flooring Contracting Services, and Plumbing Contracting Services; and B) The Construction Task Catalogs, Specifications, including addendums, and conformance with prevailing wage scale requirements for Job Order Contracts - General Constr...
Attachments: 1. 20190129_r_JOCs 1910-1923, 2. 20190129_att_Exhibit A - BID Results, 3. 20190129_a_JOC 1910_Olympus Painting, Inc., 4. 20190129_a_JOC 1911_SBAY Construction, Inc., 5. 20190129_a_JOC 1912_Mark Scott Construction, Inc., 6. 20190129_a_JOC 1913_Rodan Builders, Inc., 7. 20190129_a_JOC 1915_Kinetics Mechanical Service, 8. 20190129_a_JOC 1916_Acco Engineered Systems, 9. 20190129_a_JOC 1918_Platinum Roofing, Inc., 10. 20190129_a_JOC 1919_Best Contracting Services, Inc., 11. 20190129_a_JOC 1920_Century Carpet, Inc., 12. 20190129_a_JOC 1922_Kinetics Mechanical Service, 13. 20190129_a_JOC 1923_ACCO Engineered Systems
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: James C. Porter, Director of Public Works
Subject: On-Call Job Order Contract Agreements and Adoption of the Job Order Contracts Task Catalog

RECOMMENDATION:
title
Adopt a resolution authorizing:

A) Job Order Contract Agreements with Olympos Painting, Inc., SBAY Construction, Inc., Mark Scott Construction, Inc., and Rodan Builders, Inc. for General Construction; Kinetics Mechanical Service, Inc. and ACCO Engineered Systems for Mechanical Works (HVAC); Platinum Roofing, Inc. and Best Contracting Services, Inc. for Roofing Contracting Services; Century Carpet, Inc. for Flooring Contracting Services; and Kinetics Mechanical Service, Inc. and ACCO Engineered Systems for Plumbing Contracting Services for the term of January 29, 2019 through January 28, 2020, each in an amount not to exceed $5,000,000 for General Construction and Mechanical Works (HVAC), and not to exceed $1,000,000 for Roofing Contracting Services, Flooring Contracting Services, and Plumbing Contracting Services; and

B) The Construction Task Catalogs, Specifications, including addendums, and conformance with prevailing wage scale requirements for Job Order Contracts - General Construction; Mechanical Works; Roofing; Flooring; and Plumbing; and

C) The Director of Public Works, or his designee, to issue Work/Job Orders, execute Change/Revision Orders, and make financial and administrative changes to executed Job Order Contract agreements.

body
BACKGROUND:
On November 19, 2013, your Board adopted Resolution No. 072896, which authorized a streamlined process for Job Order Contracts (JOCs), which allows for the preparation of task catalogs, specifications, and bid documents in conformance with prevailing wage scale requirements for JOCs, which may be adopted by your Board at the time the resulting contract is considered for award.

Public Contract Code Section 20128.5 authorizes the Boar...