File #: 18-1056    Version: 1 Name:
Type: Resolution Status: Passed
File created: 10/26/2018 Departments: PUBLIC WORKS
On agenda: 11/13/2018 Final action: 11/13/2018
Title: Adopt a resolution authorizing an amendment to the agreement with AECOM Technical Services, Inc. to provide construction management services for the Crystal Springs Dam Bridge Replacement Project, extending the term through June 14, 2019, and increasing the amount by $219,381 to $4,318,363.
Attachments: 1. 20181113_r_AECOM, 2. 20181113_a_AECOM, 3. 20181113_att_AECOM - Exhibit B
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: James C. Porter, Director of Public Works
Subject: Amendment to the Agreement with AECOM Technical Services, Inc. for - Crystal Springs Dam Bridge Replacement Project

RECOMMENDATION:
title
Adopt a resolution authorizing an amendment to the agreement with AECOM Technical Services, Inc. to provide construction management services for the Crystal Springs Dam Bridge Replacement Project, extending the term through June 14, 2019, and increasing the amount by $219,381 to $4,318,363.
body

BACKGROUND:
On November 17, 2015, your Board adopted Resolution No. 074208, which authorized the Agreement with AECOM Technical Services, Inc. (AECOM) for construction management services for the Crystal Springs Dam Bridge (CSDB) Replacement Project (Project) in the amount of $2,230,458. The services to be provided in accordance with the Agreement included: construction project management, construction inspection, bridge construction oversight and coordination, compliance with the plans and specifications, compliance with federal funding requirements, and project construction coordination for the CSDB Replacement Project.

On June 6, 2017, your Board adopted Resolution No. 075246, which authorized Amendment No. 1 to the agreement with AECOM to increase the agreement amount by $1,296,775 to $3,527,233 to continue to provide ongoing construction management and inspection services.

On March 27, 2018, your Board adopted Resolution No. 075808, which authorized Amendment No. 2 to the agreement with AECOM to increase the agreement amount by $571,749 to $4,098,982 to continue to provide ongoing construction management and project closeout services.

DISCUSSION:
Amendment No. 3 extends the term through June 14, 2019 and increases the not-to-exceed amount of the agreement by $219,381. Kiewit Infrastructure West Co. (Kiewit) is the Contractor for the Project and began work on the...