Title: Adopt a resolution rejecting the bid received for the Reconstruction and Cape Seal of Madrid Avenue, Sevilla Avenue, and Sonora Avenue Project in the El Granada Area.
Attachments: 1. 20180807_r_Recon Madrid Reject
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: James C. Porter, Director of Public Works
Subject: Reconstruction and Cape Seal of Madrid Avenue, Sevilla Avenue, and Sonora Avenue Project in the El Granada Area, [County Project No. RW803, Project File No. E4987000]

RECOMMENDATION:
title
Adopt a resolution rejecting the bid received for the Reconstruction and Cape Seal of Madrid Avenue, Sevilla Avenue, and Sonora Avenue Project in the El Granada Area.

body
BACKGROUND:
On January 23, 2018, your Board adopted Resolution No. 075689, which "streamlined" the bid process for projects to be constructed during the 2018 construction season.

The projects are maintenance-type projects that do not have long lead times for design, are not considered controversial requiring specific property owner input, and that do not require state or federal grant approvals, which have not previously been approved by your Board, or require extensive permit approvals from regulatory agencies. Authorizing the Director of Public Works to develop plans and specifications and to call for bids for these types of projects at one time, reduces overall project delivery schedules and reduces administrative staff time for these types of projects.

The Reconstruction and Cape Seal of Madrid Avenue, Sevilla Avenue, and Sonora Avenue Project in the El Granada Area Project (Project) is considered a maintenance type project, as it reconstructs the base of the roadway, but does not otherwise significantly change the roadway's existing surface features.

DISCUSSION:
On Wednesday, July 11, 2018, one bid was received for this Project, which was subsequently referred to this office for analysis and recommendation. The bid submitted by Galeb Paving, Inc. in the amount of $726,156 is significantly higher than the Engineer's Estimate of $486,000. Therefore, the Department is recommending that the bid received from Galeb Paving, Inc's for thi...

Click here for full text