File #: 18-561    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/22/2018 Departments: BOARD OF SUPERVISORS DISTRICT 3
On agenda: 7/10/2018 Final action: 7/10/2018
Title: Measure K: Adopt a resolution authorizing a one-time grant of district-specific Measure K funds, not to exceed $50,000, to Cedar Street Paving LLC for installation of paving and a bioswale on the 1300 block of Cedar Street in Montara, and authorizing the County Manager, or his/her designee, to prepare and execute the grant agreement.
Sponsors: Don Horsley
Attachments: 1. 20180710_r_Cedar Street Paving LLC, 2. 20180710_a_Cedar Street Paving LLC
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: John L. Maltbie, County Manager
Subject: Use of District-Specific Measure K Funds - Supervisorial District 3

RECOMMENDATION:
title
Measure K: Adopt a resolution authorizing a one-time grant of district-specific Measure K funds, not to exceed $50,000, to Cedar Street Paving LLC for installation of paving and a bioswale on the 1300 block of Cedar Street in Montara, and authorizing the County Manager, or his/her designee, to prepare and execute the grant agreement.
body
BACKGROUND:
Measure K is the half-cent general sales tax initially approved by San Mateo County voters in November 2012 and extended in November 2016 for a total of thirty years. The Board of Supervisors ("Board") and County staff have conducted study sessions and community outreach efforts to inform priorities for Measure K spending for FY2017-19.

On May 16, 2017, the Board approved the FY 2017-19 Measure K allocation plan in which the County anticipates Measure K receipts of approximately $81.6 million annually. The plan included $7 million in one-time loans or grants during FY 2017-19, divided equally among the five supervisorial districts, for district-specific needs and projects. District 3 has submitted a request to use its district-specific Measure K funds as shown below and described in the Project Summary section of this memorandum:
District/Project
Amount
District 3 (Supervisor Don Horsley) - Cedar Street Paving LLC: for installation of paving and a bioswale on the 1300 block of Cedar Street in Montara.
$50,000

This item is consistent with the criteria for district-specific Measure K funds, which were developed during the initial round of district-specific allocations and approved by the Board in April 2015.

PROJECT SUMMARY:
This is a request to authorize a one-time grant to Cedar Street Paving LLC, and resulting grant agreement in an amount not to exceed $50,000 to provi...