San Mateo County Logo
File #: 16-347    Version: 1 Name:
Type: Resolution Status: Passed
File created: 6/5/2017 Departments: PUBLIC WORKS
On agenda: 6/27/2017 Final action: 6/27/2017
Title: Adopt a resolution authorizing: A) The President of the Board to execute an agreement with Salt River Construction Corporation, in the amount of $1,169,750 for the Coyote Point Marina 2017 Maintenance Dredging Project; and B) The Director of Public Works to execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $117,000, or approximately 10% of the agreement amount.
Attachments: 1. 20170627_att_Exhibit A_Award 2017 CPM Dredging (OD432), 2. 20170627_r_Award 2017 CPM Dredging (OD432)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: James C. Porter, Director of Public Works
Subject: Coyote Point Marina 2017 Maintenance Dredging Project [County Project No. OD432; County Project File No. E4953000]

RECOMMENDATION:
title
Adopt a resolution authorizing:

A) The President of the Board to execute an agreement with Salt River Construction Corporation, in the amount of $1,169,750 for the Coyote Point Marina 2017 Maintenance Dredging Project; and

B) The Director of Public Works to execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $117,000, or approximately 10% of the agreement amount.

body
BACKGROUND:
The Coyote Point Marina periodically requires maintenance dredging due to siltation of its channels and boat slips from San Francisco Bay's tidal action. Previous maintenance dredging in 2010, 2006, and 2002 included the Marina's main channel, most of the secondary channels used by tenants to access their boat slips, and specific boat slips. Since the completion of those dredging episodes, new siltation has occurred that is once again affecting navigation in portions of the Marina.

On June 28, 2016, your Board approved a contract with TranSystems, Inc. to provide consultant services to prepare plans and specifications and to secure permits for the Coyote Point Marina 2017 Maintenance Dredging Project ("Project"). On May 16, 2017, your Board adopted Resolution No. 075201, which adopted the Project plans and specifications, including conformance with prevailing wage scale requirements and calling for sealed bids for the above-mentioned project. The necessary agency permits for the Project have been obtained and the Project qualifies for a Categorical Exemption pursuant to the California Environmental Quality Act (CEQA) Guidelines for Implementation, which will be filed by the San Francisc...