Legislation Details

File #: 26-802    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 8/31/2026 Departments: PUBLIC WORKS
On agenda: 9/29/2026 Final action:
Title: Adopt a resolution authorizing Amendment No. 3 to the Agreement with Vista Environmental Consulting for on-call hazardous materials assessment and related services, increasing the not-to-exceed amount by $150,000, for a new not-to-exceed amount of $775,000 with no change in term.
Attachments: 1. 20260929_r_Amendment No. 3 to Vista Environmental Consulting, 2. 20260929_a_Amend #3 Vista Environmental Partially Signed
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: Tory A. Newman, Director of Public Works
Subject: Amendment No. 3 to the Agreement with Vista Environmental Consulting

RECOMMENDATION:
title
Adopt a resolution authorizing Amendment No. 3 to the Agreement with Vista Environmental Consulting for on-call hazardous materials assessment and related services, increasing the not-to-exceed amount by $150,000, for a new not-to-exceed amount of $775,000 with no change in term.

body
BACKGROUND:
On June 28, 2022, this Board adopted Resolution No. 079012(p), authorizing an Agreement with Vista Environmental Consulting for on-call hazardous materials assessment and related services for the Department of Public Works (Department) capital projects. The initial agreement term was from June 28, 2022 through June 27, 2025 for an amount not to exceed $300,000.

On September 4, 2024, as authorized by Resolution No. 079012(a-p), the Director of Public Works executed Amendment No. 1 increasing the not-to-exceed amount by $25,000 with no change in term.

On February 25, 2025, this Board adopted Resolution No. 080953, authorizing Amendment No. 2, which extended the contract term through June 28, 2027, and increased the not-to-exceed amount by $300,000, for a revised total of $625,000.

DISCUSSION:
The Department recommends executing Amendment No. 3 to increase the contract amount by $150,000, bringing the new not-to-exceed amount to $775,000 with no change in term. This additional funding will support ongoing hazardous materials assessment, testing, and monitoring services for multiple active projects, including the County Office Building 1 Renovation and Modernization Project, the Hall of Justice Court Tenant Improvements Project, and other anticipated Capital Improvement Plan projects.

Amending the existing agreement leverages Vista Environmental Consulting’s site-specific project familiarity and active deployment...

Click here for full text