Legislation Details

File #: 26-477    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 5/13/2026 Departments: PUBLIC WORKS
On agenda: 6/9/2026 Final action:
Title: Adopt a resolution increasing the Director of Public Works', or designee's, authority to execute change orders to the construction agreement with Rodan Builders, Inc. for the San Mateo Medical Center Prevent Self Harm and Ligature Project to increase the not-to-exceed amount of $3,908,677 by an additional $25,000, for a new not-to-exceed amount of $3,933,677.
Attachments: 1. 20260609_r_Increase NTE for Rodan Builders Inc. Agreement
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: Tory A. Newman, Director of Public Works
Subject: Increase the Not-to-Exceed Amount of the Agreement with Rodan Builders, Inc. for the San Mateo Medical Center Prevent Self Harm and Ligature Project (Project No. P30F1)

RECOMMENDATION:
title
Adopt a resolution increasing the Director of Public Works', or designee's, authority to execute change orders to the construction agreement with Rodan Builders, Inc. for the San Mateo Medical Center Prevent Self Harm and Ligature Project to increase the not-to-exceed amount of $3,908,677 by an additional $25,000, for a new not-to-exceed amount of $3,933,677.

body
BACKGROUND:
On March 23, 2021 this Board adopted Resolution No. 078091 authorizing an Agreement with Rodan Builders, Inc. for the San Mateo Medical Center Prevent Self Harm and Ligature Project (Project) in the amount of $3,310,180 and authorized the Director of Public Works to execute subsequent change orders to grant time extensions for project completion and payment up to a maximum amount not-to-exceed $3,641,198.

On March 26, 2024, this Board adopted Resolution No. 080262 which increased the Director of Public Works, or designee, authority to execute changes to the Agreement with Rodan Builders, Inc. by an additional $165,200 for a new not-to-exceed amount of $3,806,398.

On June 10, 2025, this Board adopted Resolution No. 081282 which increased the not-to-exceed amount by an additional $102,279 for a new not-to-exceed amount of $3,908,677.

During Phase 1 and Phase 2 of construction, the Project encountered unanticipated building conditions which required modifications to meet building code requirements. Additional changes to lighting fixtures and material mitigations were necessary to comply with anti-ligature requirements.

Phase 3 of construction started in January 2025 in the Psychiatric Emergency Services (PES) Unit on the 1st Floor...

Click here for full text