Special Notice / Hearing: None__
Vote Required: Majority
To: Honorable Board of Supervisors
From: Michael P. Callagy, County Executive
Sam Lin, Interim Director, Project Development Unit
Subject: Amendment to Truebeck, Inc. Construction Manager Agreement for Campus Infrastructure Improvement, Project Budget
RECOMMENDATION:
title
Adopt a resolution authorizing the County Executive, or designee, to execute an amendment to the Agreement with Truebeck Construction, Inc., incorporating the initial project scope expenses incurred on the Campus Infrastructure Improvement Project scope, increasing the agreement by an amount not to exceed $195,378, and establishing an updated contract value of $191,812,873.
body
BACKGROUND:
In March 2017, this Board considered recommendations for generational capital improvements to address, among other things: (1) reliance on increasingly outdated facilities and infrastructure; (2) high maintenance and operational costs; (3) overutilization of leased space that is subject to potentially uncontrolled cost growth; (4) rising environmental standards; and (5) service and programming improvements needed to better serve residents.
This Board thereafter directed staff to pursue various capital projects including the Lathrop House Relocation, Parking Structure 2 (PS2), and County Office Building 3 (COB3), collectively referred to as the County Government Center Projects.
This Board subsequently approved the Campus Infrastructure Improvements Project (Infrastructure Project). The Infrastructure Project included, among other things, landscape, hardscape, and infrastructure improvements creating a cohesive campus, providing accessibility infrastructure, and increasing Americans with Disabilities Act (ADA) compliance. To avoid demolishing newly constructed infrastructure, the Infrastructure Project was to occur concurrently with work by the Department of Public Works to complete necessary waterproofing and repairs fo...