Skip to main content
San Mateo County Logo
File #: 25-610    Version: 1 Name:
Type: Resolution Status: Agenda Ready
File created: 6/4/2025 Departments: COUNTY EXECUTIVE
On agenda: 6/24/2025 Final action:
Title: Measure K: Adopt a resolution authorizing the Interim Director of the Project Development Unit, or designee, to use the Design-Bid-Build Best Value contractor procurement, pursuant to Public Contract Code ?20155, for construction of the new Fire Station No. 59, located in Pescadero.
Attachments: 1. 20250624_r_Pescadero Station No.pdf
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: Michael P. Callagy, County Executive Officer
Sam Lin, Interim Director, Project Development Unit
Subject: Best Value Procurement for Fire Station No. 59

RECOMMENDATION:
title
Measure K: Adopt a resolution authorizing the Interim Director of the Project Development Unit, or designee, to use the Design-Bid-Build Best Value contractor procurement, pursuant to Public Contract Code ?20155, for construction of the new Fire Station No. 59, located in Pescadero.

body
BACKGROUND:
Public Contract Code ?20155 establishes a program for ten counties, including the County of San Mateo, authorizing the award of Design-Bid-Build construction contracts for projects of more than $1,000,000 to the bidder who offers the proposal that affords the best value to the County based upon the evaluation of certain pre-identified qualitative criteria, including price and contractor qualifications.

This approach allows consideration of qualitative factors such as contractor experience with complex site conditions, project staffing, and the proposed technical approach when pre-qualifying and selecting contractors. The County has previously used best value procurement for Design-Build and Construction-Manager-at-Risk contracts.

DISCUSSION:
Fire Station No. 59 project presents unique challenges that warrant the flexibility provided by best value procurement. The Fire Station is a critical emergency services facility located in rural Pescadero. Due to its location and site conditions, the project faces a range of conditions requiring strong technical expertise including:
* Completion of ground improvements that require removal of existing soil to mitigate risks associated with liquefaction during an earthquake.
* Installation of a specialized foundation design to mitigate local seismic risk.
* Underground work managing power lines and well water system connection.
*...