Skip to main content
San Mateo County Logo
File #: 25-714    Version: 1 Name:
Type: Resolution Status: Passed
File created: 7/15/2025 Departments: PUBLIC WORKS
On agenda: 8/12/2025 Final action: 8/12/2025
Title: Adopt a resolution waiving the Request for Proposals (RFP) process and authorizing Amendment No. 3 to the agreement with Smith-Karng Architecture for the San Mateo Medical Center Prevent Self-Harm and Ligature Project, increasing the amount by $40,000, to a new not to exceed amount of $228,636 and extending the term of the agreement through December 30, 2025.
Attachments: 1. 20250812_r_Smith-Karng Architecture A3, 2. 20250812_a_Smith-Karng Architecture_A3_partially signed, 3. 0051_1_20250812_r_Smith-Karng Architecture A3.pdf, 4. 0051_2_20250812_a_Smith-Karng Architecture_A3_partially signed.pdf
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: Ann M. Stillman, Director of Public Works
Subject: Amendment to the Agreement with Smith-Karng Architecture for the San Mateo Medical Center Prevent Self-Harm and Ligature Project

RECOMMENDATION:
title
Adopt a resolution waiving the Request for Proposals (RFP) process and authorizing Amendment No. 3 to the agreement with Smith-Karng Architecture for the San Mateo Medical Center Prevent Self-Harm and Ligature Project, increasing the amount by $40,000, to a new not to exceed amount of $228,636 and extending the term of the agreement through December 30, 2025.

body
BACKGROUND:
On February 1, 2023, the Director of Public Works executed an Agreement with Smith-Karng Architecture for architectural and engineering services for the San Mateo Medical Center Prevent Self-Harm and Ligature and Psychiatric Emergency Services (PES) Youth Crisis Stabilization Unit Renovation Projects (Projects) from February 1, 2023 through August 30, 2024, in the amount of $107,596.

The Director of Public Works executed Amendment No. 1 extending the term of the Agreement through December 31, 2024 and Amendment No. 2 increasing the not-to-exceed amount by an additional $81,040 for a new not-to-exceed amount of $188,636 and extending the term of the Agreement through September 30, 2025.

DISCUSSION:
Smith-Karng Architecture is the Architect of Record with the California Department of Healthcare Access and Information (HCAI) for the Projects.

In January 2025, Phase 3 of construction started in the PES Unit on the 1st Floor of the Diagnostic and Treatment Building. Unanticipated existing building conditions and additional improvement requests required additional work to meet building code requirements. Revised construction documents were necessary to submit to HCAI for review and approval.
Based on the additional cost of the added design fees and HCAI revisions and req...