San Mateo County Logo
File #: 24-384    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/25/2024 Departments: PUBLIC WORKS
On agenda: 5/21/2024 Final action: 5/21/2024
Title: Adopt a resolution increasing the Director of Public Works' or Director's designee's authority to execute change orders to the Agreement with Siemens Industry, Inc. for the San Mateo Medical Center Fire Alarm System Upgrade Project, increasing the not-to-exceed amount by an additional $210,000 for a new not-to-exceed amount of $2,112,450.
Attachments: 1. 20240521_r_Amendment to Agreement with Siemens
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: Ann M. Stillman, Director of Public Works
Subject: Increase the Not to Exceed Amount of the Agreement with Siemens Industry, Inc. for the San Mateo Medical Center Fire Alarm System Upgrade Project (PF308)

RECOMMENDATION:
title
Adopt a resolution increasing the Director of Public Works' or Director's designee's authority to execute change orders to the Agreement with Siemens Industry, Inc. for the San Mateo Medical Center Fire Alarm System Upgrade Project, increasing the not-to-exceed amount by an additional $210,000 for a new not-to-exceed amount of $2,112,450.
body

BACKGROUND:
On December 10, 2019, this Board adopted Resolution No. 077117 authorizing an agreement with Siemens Industry, Inc. for the San Mateo Medical Center Fire Alarm System Upgrade Project (Project) for a not-to-exceed amount of $1,902,450 through December 9, 2021.

By authority of Resolution No. 077117, the designee for the Director of Public Works extended the term of the agreement through June 28, 2024.

The Project has faced numerous challenges due to design compliance changes and restrictions set forth by Health Care Access and Information (HCAI). Additionally, the Project Development Unit had projects underway, which required a delay to the Project's start date due to the interconnectivity of the systems. During construction of the Project, it was discovered that modifications to some of the device locations were required as the plans for the existing fire alarm system were not always consistent with field conditions, which affected the Project schedule. Construction in multiple buildings simultaneously was limited by HCAI, which has caused the Project to incur additional costs for the contractor to mobilize and demobilize crews for each building in construction.

DISCUSSION:
As the Project nears completion, the Department of Public Works (Department) anticipates ...

Click here for full text