San Mateo County Logo
File #: 22-447    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/18/2022 Departments: PUBLIC WORKS
On agenda: 6/14/2022 Final action: 6/14/2022
Title: Adopt a resolution authorizing: A) The President of the Board to execute an agreement with Granite Rock Company, for the Reconstruction of Encina Avenue from Middlefield Road to End in the North Fair Oaks Area, in the amount of $1,678,992.50; and B) The Director of Public Works to: 1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $167,899.25 or approximately 10 percent of the agreement amount; and 2. Approve payment up to the not-to-exceed amount of $1,846,891.75 for items requiring adjustment based on unit bid prices without execution of a change order; and 3. File a Notice of Exemption for a California Environmental Quality Act Categorical Exemption.
Attachments: 1. 20220614_r_Reconstruction_of_Encina_Avenue_Award Final, 2. 20220614_att_Reconstruction_of_Encina_Avenue_Award_Exhibit A Final
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: Ann M. Stillman, Interim Director of Public Works
Subject: Reconstruction of Encina Avenue - North Fair Oaks Area
[County Project No. RW935, Project File No. E5044]


RECOMMENDATION:
title
Adopt a resolution authorizing:

A) The President of the Board to execute an agreement with Granite Rock Company, for the Reconstruction of Encina Avenue from Middlefield Road to End in the North Fair Oaks Area, in the amount of $1,678,992.50; and

B) The Director of Public Works to:

1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $167,899.25 or approximately 10 percent of the agreement amount; and

2. Approve payment up to the not-to-exceed amount of $1,846,891.75 for items requiring adjustment based on unit bid prices without execution of a change order; and

3. File a Notice of Exemption for a California Environmental Quality Act Categorical Exemption.

body
BACKGROUND:
On June 18, 2002, this Board adopted Resolution Nos. 065329 and 065330, which established minimum road standard options and a priority list for road improvements in the North Fair Oaks area, respectively.

Encina Avenue, from Middlefield Road to End, is the next street on the North Fair Oaks area road priority list to be considered for reconstruction. The Reconstruction of Encina Avenue from Middlefield Road to End (Project) includes one block, from Middlefield Road to Oak Drive, in which the County/Town of Atherton (Town) jurisdictional boundary is at the center of the road right-of-way. The Department surveyed all property owners along the street in the unincorporated area to determine the minimum road standards to be used in the design of the road improvements. The road standards to be used for this Project are based on the results of the property owner survey and discussions with the Town. From Oak Dr...