Subject: Amendment to an Agreement with DKS Associates for preparation of the Comprehensive Transportation Management Plan pursuant to San Mateo County Local Coastal Program Policy 2.53
RECOMMENDATION:
title
Adopt a resolution authorizing an amendment to the agreement with DKS Associates for preparation of the Comprehensive Transportation Management Plan extending the agreement term through December 31, 2017, not-to-exceed increasing the amount by $65,060, for a new amount not-to-exceed $650,011.
body
BACKGROUND:
In 2012, the Board of Supervisors adopted the Midcoast Update to San Mateo County Local Coastal Program (LCP). Policy 2.53 of the adopted LCP calls for the County to develop a Comprehensive Transportation Management Plan to evaluate the cumulative traffic impacts of residential development, including single-family, two-family, multi-family and second dwelling units, on Highway 1, Highway 92 and other arterial roads throughout the Midcoast and in the City of Half Moon Bay.
On May 20, 2014, the Board of Supervisors executed an agreement with DKS Associates to develop the Comprehensive Transportation Management Plan (the "Plan"). The agreement was for an amount not to exceed $494,975, with a term end date of August 25, 2015.
On July 7, 2015, the Board of Supervisors executed an amendment to the agreement to allow DKS Associates to provide additional services, not-to-exceed increasing the amount by $89,976, for a new amount not-to-exceed $584,951 and extending the term through December 31, 2016.
Significant stakeholder feedback has focused on determining how to procced with either signalization or implementation of a roundabout at the intersection of Highway 1 and Cypress Avenue in Moss Beach. This intersection has been identified in the Comprehensive Transportation Management Plan ...