Special Notice / Hearing: None__
Vote Required: Majority
To: Honorable Board of Supervisors
From: Ann M. Stillman, Director of Public Works
Subject: 2025 Job Order Contracts for General Construction, Mechanical Works (HVAC), Roofing, Flooring, Plumbing, Electrical and Lighting, Painting, and Hazardous Materials [Job Order Contract Nos. JOC-2501 through JOC-2521]
RECOMMENDATION:
title
Adopt a resolution:
A) Adopting the construction task catalog, specifications, and conformance with prevailing wage scale requirements for 2025 Job Order Contracts for General Construction; Mechanical Works (HVAC); Roofing; Flooring; Plumbing; Electrical and Lighting; Painting; and Hazardous Materials; and
B) Authorizing agreements with Sbay Construction, Inc., Olympos Construction, Inc., Prime Painting Contractors, Inc., Angeles Contractor, Inc., and Rodan Builders, Inc. for General Construction; Bayside Mechanical, Inc., Mesa Energy Systems and ACCO Engineered Systems for Mechanical Works (HVAC); Best Contracting Services, Inc. and Angeles Contractor, Inc. for Roofing Contracting Services; Pro Spectra Contract Flooring for Flooring Contracting Services; Angeles Contractor, Inc. and Ray Scheidts, Inc. for Electrical and Lighting Contracting Services; and Olympos Construction, Inc. and AG Painting Services for Painting Contracting for the term of January 30, 2025 through January 29, 2026 in an amount not to exceed $5,000,000 each for General Construction and Mechanical Works (HVAC); $2,000,000 each for Roofing, Flooring, and Electrical and Lighting; and $1,000,000 each for Painting with a total maximum fiscal obligation for all agreements combined is $52,000,000; and
C) Authorizing the Director of Public Works, or designee, to issue Work/Job Orders, execute Change/Revision Orders, and make financial and administrative changes to executed Job Order Contract agreements.
body
BACKGROUND:
On November 19, 2013, this Board adopted Resolution No. 072896, which...