Title: Adopt a resolution: A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the Wurr Road and Pescadero Creek Road Culverts Improvement Project; and B) Authorizing and directing the President of the Board of Supervisors to execute an agreement with JDB & Sons Construction, Inc, in the amount of $1,190,490.00 for the Wurr Road and Pescadero Creek Road Culverts Improvement Project; and C) Authorizing the Director of Public Works to: 1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $119,049.00, or approximately 10 percent of the agreement amount; and 2. Execute payment up to the not-to-exceed amount of $1,309,539.00 for items requiring adjustment based on unit bid prices without execution of a change order.
Attachments: 1. 20260623_r_Wurr and Pesc Ck Rd Culverts_AdoptAward, 2. 20260623_att_Exhibit A_Wurr and Pesc Ck Rd Culverts_AdoptAward
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: Tory A. Newman, Director of Public Works
Subject: Wurr Road and Pescadero Creek Road Culverts Improvement Project
[County Project No. RW308; County Project File No. E5084]

RECOMMENDATION:
title
Adopt a resolution:

A) Adopting plans and specifications, including conformance with prevailing wage scale requirements, for the Wurr Road and Pescadero Creek Road Culverts Improvement Project; and

B) Authorizing and directing the President of the Board of Supervisors to execute an agreement with JDB & Sons Construction, Inc, in the amount of $1,190,490.00 for the Wurr Road and Pescadero Creek Road Culverts Improvement Project; and

C) Authorizing the Director of Public Works to:

1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $119,049.00, or approximately 10 percent of the agreement amount; and

2. Execute payment up to the not-to-exceed amount of $1,309,539.00 for items requiring adjustment based on unit bid prices without execution of a change order.

body
BACKGROUND:
Wurr Road, Pescadero Creek Road, and Cloverdale Road are County maintained roads in the unincorporated Loma Mar Area, within the Pescadero-Butano Watershed. There are twelve (12) culvert (pipe) work locations to be improved, which locations were identified as priority locations in the Pescadero-Butano Watershed County Road Inventory and Sediment Assessment conducted in 2022. These improvements are required to comply with Total Maximum Daily Load for the Sediment and Habitat Enhancement Plan adopted in 2018 by the California Regional Water Quality Control Board.

The Department of Public Works ("Department") will construct nine (9) of the twelve (12) sites (Sites 94, 102, 119, 128.1, 265, 265.1, 266, 270, and 270.1) as part of the Wurr Road, Pescadero Creek Road, and Cloverdale Road Cul...