File #: 25-228    Version: 1 Name:
Type: Resolution Status: Passed
File created: 2/4/2025 Departments: COUNTY EXECUTIVE
On agenda: 3/25/2025 Final action: 3/25/2025
Title: Measure K: Adopt a resolution authorizing: A) The President of the Board to execute an agreement with Perkins+Will to provide architectural and engineering services for CDF Fire Station No. 59 located in the town of Pescadero, for the term of March 1, 2025 through March 31, 2028, in an amount not to exceed $2,717,851; and B) The Director of Project Development Unit or designee to execute amendments to the Architectural and Engineering agreement with Perkins+Will up to an aggregate amount not to exceed $135,893.
Attachments: 1. 20250325_r_PerkinsWill_CDF Pescadero.pdf, 2. 20250325_a_perkins and will, inc.pdf, 3. 20250325_att_20231018_request for proposal_on-call architectural and engineering design and space planning services.pdf, 4. 20250325_att_perkin and will proposal.pdf
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: Michael P. Callagy, County Executive
Sam Lin, Project Development Unit Director
Subject: Fire Station No. 59 Architectural and Engineering Services Agreement

RECOMMENDATION:
title
Measure K: Adopt a resolution authorizing:

A) The President of the Board to execute an agreement with Perkins+Will to provide architectural and engineering services for CDF Fire Station No. 59 located in the town of Pescadero, for the term of March 1, 2025 through March 31, 2028, in an amount not to exceed $2,717,851; and

B) The Director of Project Development Unit or designee to execute amendments to the Architectural and Engineering agreement with Perkins+Will up to an aggregate amount not to exceed $135,893.

body
BACKGROUND:
In January 2017, the County of San Mateo formed the Project Development Unit (PDU) to manage all new construction projects, including the replacement of Fire Station 59. This station is a vital regional asset, serving the South Coast and acting as a strategic base for wildfire response.

The current station, located in a floodplain, suffers from yearly flooding, mold, and plumbing system failures, impacting access and service to the Pescadero community. Seasonal flooding isolates the station, delaying emergency response and compromising safety. Moreover, the existing facility lacks adequate space for staffing and equipment, hindering CalFire's ability to meet community needs, especially during peak fire seasons. To address these critical issues, the County Board of Supervisors approved the construction of a new fire station on a 1.75-acre site at 350-360 Butano Cut Off.

DISCUSSION:
On October 18, 2023, the County issued an RFP to select an architect for the new Fire Station No. 59 and PBK Architects was awarded the contract. Following completion of schematic design, and in view of site conditions not apparent at contract award, the Coun...

Click here for full text