File #: RES-070064    Version: 1 Name:
Type: Resolution Status: Passed
File created: 4/28/2009 Departments: BOARD OF SUPERVISORS
On agenda: 4/28/2009 Final action: 4/28/2009
Title: RESOLUTION: 1) AWARDING AND AUTHORIZING EXECUTION OF A CONTRACT WITH HALF MOON BAY GRADING & PAVING, INC. IN THE AMOUNT OF $184,523 FOR THE RECONSTRUCTION OF MILLS AVENUE PROJECT IN THE WEST MENLO PARK AREA (PROJECT NO. RH303, F-36 [324C]), AND 2) AUTHORIZING THE DIRECTOR OF PUBLIC WORKS TO EXECUTE CONTRACT CHANGE ORDERS IN AN AMOUNT NOT TO EXCEED $27,677 OR APPROXIMATELY 15% OF THE CONTRACT AMOUNT.
Attachments: 1. 371205