San Mateo County Logo
File #: 24-580    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/15/2024 Departments: PUBLIC WORKS
On agenda: 6/25/2024 Final action: 6/25/2024
Title: Adopt a resolution authorizing: A) The President of the Board to execute an agreement with RK Engineering Inc. for the Santa Cruz Avenue/Alameda de las Pulgas Complete Street Project, in the amount of $5,757,250 and B) The Director of Public Works to: 1. Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $575,725 or approximately 10% of the agreement amount; and 2. Approve payment up to the not to exceed amount of $6,332,975 for items requiring adjustment based on unit bid prices without execution of a change order.
Attachments: 1. 20240625_r_SCA ALDP Award, 2. 20240625_att_Award Exhibit A SCA ALDP, 3. 0110_1_20240625_r_SCA ALDP Award.pdf

Special Notice / Hearing:                         None__

      Vote Required:                         Majority

 

To:                      Honorable Board of Supervisors

From:                      Ann M. Stillman, Director of Public Works

Subject:                      Santa Cruz Avenue/Alameda de las Pulgas Complete Street Project

County Project No. RW934; Project File No. E5043

 

RECOMMENDATION:

title

Adopt a resolution authorizing:

 

A)                     The President of the Board to execute an agreement with RK Engineering Inc. for the Santa Cruz Avenue/Alameda de las Pulgas Complete Street Project, in the amount of $5,757,250 and

 

B)                     The Director of Public Works to:

 

1.                     Execute subsequent change orders to grant time extensions for project completion and payment up to a maximum aggregate amount not to exceed $575,725 or approximately 10% of the agreement amount; and

 

2.                     Approve payment up to the not to exceed amount of $6,332,975 for items requiring adjustment based on unit bid prices without execution of a change order.

 

body

BACKGROUND:

On March 28, 2023, this Board adopted Resolution No. 079531, which authorized the Director of Public Works, or designee, to file an application for funding assigned to the

Metropolitan Transportation Commission (MTC) committing any necessary matching funds and stating assurance to complete the Project. Subsequently, on March 22, 2024 MTC approved the 2023 Regional Active Transportation Program Cycle 6 (ATP) grant in the amount of $5,435,000 for the Santa Cruz Avenue/Alameda de las Pulgas Complete Street Project (Project).

 

On April 23, 2024 this Board adopted Resolution No. 080307, which adopted plans and specifications, including conformance with prevailing wage scale requirements and called for sealed proposals for the Santa Cruz Avenue/Alameda de las Pulgas Complete Street Project.

 

DISCUSSION:

On Thursday, June 6, 2024, bids were accepted for the Project and subsequently referred to Public Works for checking and recommendation. The bid of:

 

RK Engineering Inc.

3450 3rd Street, Unit D4

San Francisco, CA 94124

 

at $5,757,250 was the lowest responsible bid received for the work. The Engineer’s Estimate was $6,984,000. A summary of the bids received is attached as Exhibit “A”.

 

Department staff has determined that this Project qualifies for a Statutory Exemption pursuant to Section 28102.25 (SB922) of the California Environmental Quality Act (CEQA) Guidelines for Implementation, which provides that specific transportation plans and projects, such as pedestrian and bicycle plans and facilities are exempt from review.  Department staff has issued Notice of Exemption for a CEQA Statutory Exemption for this Project on December 20, 2023.

 

County Attorney has reviewed and approved the resolution as to form.

 

FISCAL IMPACT:

The total estimated cost for construction is $6,332,975, which includes authorization for up to $575,725 in change orders as the work is bid on a unit price basis.  The contingency is used to pay the contractor for any unforeseen conditions not anticipated in the construction agreement documents. 

 

The Project is proposed to be financed as follows:

 

* The ATP Cycle 6 grant funding amount is $5,435,000 for construction.

 

**Resolution No. 078188, executed by this Board on May 18, 2021, authorized the Director of Public Works to enter into agreements with public agencies or utility companies for work less than $200,000 proposed to be done in conjunction with County road projects.

 

Funding for this Project will primarily be from the ATP Cycle 6. The Project will initially be financed by the Road Fund as the ATP Cycle 6 funds are received on a reimbursable basis.

 

There is no impact on the General Fund.

 

Attachment: Exhibit “A” - Summary of Bids Received