Title: Adopt a resolution: A) Adopting plans and specifications, including conformance with prevailing wage scale requirements for the Santa Cruz Avenue/Alameda de las Pulgas Complete Street Project - West Menlo Park Area; and B) Authorizing the Director of Public Works to call for sealed proposals to be received by Thursday May 16, 2024 at 2:30 p.m., in the office of the County Executive Officer/Clerk of the Board of Supervisors; and C) Authorizing the Director of Public Works to extend the call for bids and bid opening up to sixty (60) calendar days beyond the time and date originally set forth by the Board of Supervisors.
Attachments: 1. 20240423_r_SCA-ADLP
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: Ann M. Stillman, Director of Public Works
Subject: Santa Cruz Avenue/Alameda de las Pulgas Complete Street Project - West Menlo Park Area [County Project No. RW934; County Project File No. E5043]

RECOMMENDATION:
title
Adopt a resolution:

A) Adopting plans and specifications, including conformance with prevailing wage scale requirements for the Santa Cruz Avenue/Alameda de las Pulgas Complete Street Project - West Menlo Park Area; and

B) Authorizing the Director of Public Works to call for sealed proposals to be received by Thursday May 16, 2024 at 2:30 p.m., in the office of the County Executive Officer/Clerk of the Board of Supervisors; and

C) Authorizing the Director of Public Works to extend the call for bids and bid opening up to sixty (60) calendar days beyond the time and date originally set forth by the Board of Supervisors.

body
BACKGROUND:
On October 20, 2020 this Board adopted Resolution No. 077821, which approved the Santa Cruz Avenue/Alameda de las Pulgas Complete Street Project (Project) and supported an application to the San Mateo Transportation Authority for pedestrian and bicycle program funding for design and permitting of the Project.

On March 28, 2023 this Board adopted Resolution No. 079531, which authorized the Director of Public Works, or designee, to file an application for funding assigned to the
Metropolitan Transportation Commission (MTC) committing any necessary matching funds and stating assurance to complete the Project.

The MTC, administers state and federal funds to support programs that make walking and biking better travel options through their 2023 Regional Active Transportation Program Cycle 6 (ATP Cycle 6).

The MTC Programming and Allocations Committee recommended funding the construction portion of the Project in the ATP Cycle 6. The MTC submitted the list of projects to the California Transport...