San Mateo County Logo
File #: 16-759    Version: 1 Name:
Type: Resolution Status: Passed
File created: 10/10/2017 Departments: COUNTY MANAGER
On agenda: 11/21/2017 Final action: 11/21/2017
Title: Adopt a resolution authorizing the Director of the Project Development Unit or his/her designee to: A) Negotiate and enter into an agreement for architectural and engineering professional services with Studio Gang, in an amount not to exceed $9,901,645; and B) If negotiations with Studio Gang are unsuccessful, negotiate and enter into an agreement for architectural and engineering professional services with Skidmore, Owens, & Merrill, LLP (SOM), in an amount not to exceed $9,901,645; and ; and C) Execute change orders to the Architectural and Engineering agreement with the contracted firm up to an aggregate amount not to exceed 10 percent of the agreement value.
Attachments: 1. 20171107_att_RFP Matrix, 2. 20171107_r_COB3 AE Resolution
Special Notice / Hearing: None__
Vote Required: Majority

To: Honorable Board of Supervisors
From: Deborah Bazan, Director of the Project Development Unit
Subject: County Office Building 3 Architect and Engineering Agreement

RECOMMENDATION:
title
Adopt a resolution authorizing the Director of the Project Development Unit or his/her designee to:

A) Negotiate and enter into an agreement for architectural and engineering professional services with Studio Gang, in an amount not to exceed $9,901,645; and

B) If negotiations with Studio Gang are unsuccessful, negotiate and enter into an agreement for architectural and engineering professional services with Skidmore, Owens, & Merrill, LLP (SOM), in an amount not to exceed $9,901,645; and ; and

C) Execute change orders to the Architectural and Engineering agreement with the contracted firm up to an aggregate amount not to exceed 10 percent of the agreement value.

body
BACKGROUND:
In January 2017, the County Manager's Project Development Unit (PDU) was formed to oversee and manage all ground up construction performed by the County of San Mateo. In March of 2017, your Board held a Study Session to consider the recommendations for capital improvements made in the Feasibility Studies and Master Plans to address the County's use of lease space, aging facilities, OSHPD compliance work, public accessibility and navigation, parking, environmental standards, and efficiency of employee work spaces. Direction was given to the County Manager and the PDU to move forward with the recommended capital improvements at the conclusion of the Study Session. The new approved and on-going Capital Projects total approximately $500 million and are being managed by the PDU.

Among the anticipated capital projects is a new County Office Building 3 (COB3) to be located at County Government Center. It is currently anticipated that the new building will be approximately 121,000-150,000 square feet, with five to seven...

Click here for full text